0
philcr
7y

Last week we commenced a programming project on a machine that was being built for a customer with a view to them coming to test machine in 8 working days, we spent 2.5 days re wiring due to bad electrical design, a further two days changing mechanical design, and I have had half a day coding. We now have three days before customer comes and about three weeks work to do. Might be some long days

Comments
  • 0
    Damn, that sounds rough.
  • 0
    @tisaconundrum it's the way our company works, when we design a machine designers get six months, mechanical fitters get two weeks, electrician get 1.5 weeks and programmers get two days
  • 0
    @philcr That priority is built horribly! $%^$
Add Comment